Fairfield Medical Center, River Valley Campus-v2

Fairfield Medical Center, River Valley Campus

Location: Lancaster, Ohio
Project Type: Healthcare
Contract: $3,000,000
Role: Technical Consultant — Electrical Contractor
General Contractor: The Boldt Company
Completion: 2019

Claypool Electric was hired to supplement the contracted electrical contractor who was failing to meet the schedule and provide a proper installation.

Challenges

In the winter of 2018, the project was in trouble. The schedule was not being met, there were numerous installation deficiencies, code violations and incomplete material packages. Claypool Electric was hired initially to review the project but was soon asked to take over to fix and complete the installation.

Outcome

We were able to complete the project only slightly behind schedule despite having to rework most of the existing installation.

Highlights

Claypool Electric employees worked numerous overtime hours with no reportable injuries or safety violations.

$3M

contract

OVERTIME

worked to meet schedule/span>

0

injuries or safety violations

The Ohio State University Wexner Medical Center Central Sterile Supply
Fairfield Medical Center, Project Bright
Vineyard Columbus, Grandview Campus
The Ohio State University Wexner Medical Center Central Sterile Supply-1
Fairfield Medical Center, Project Bright-1