

Hoover Dam, City of Columbus
Location: Westerville, Ohio
Project Type: Water/Waste Water
Contract: $2,000,000
Role: Electrical Subcontractor
General Contractor: Kokosing Industrial, Inc.
Completion: 2021
Hoover Dam, built in the 1950s, is a critical source of water supply for the City of Columbus. Improvements to the dam were designed to maintain the reliable water supply and extend the life of the dam.
Challenges
While some of the electrical infrastructure had been modified over the years, most of the existing equipment was original and required replacement or rehabilitation. And, with most conduits embedded in the concrete walls of the structure, tracing the existing panel circuits and wiring was difficult.
Existing systems had to be temporarily disconnected and/or relocated prior to installing new electrical distribution equipment and SCADA control systems. This required outages of the electrical gates and motorized valves that were used to control the flow of water over the dam spillway.
Process and electrical outage times were limited to short durations and weather had to be carefully monitored as heavy rainfall raised the reservoir to high levels. Adding to the challenge, the lower level of the dam was 70’ below the grade of the main building entrance and required access via the stairway.
Outcome
Throughout the course of construction, the facility continued to operate and maintain the required controlled flow of water to the City of Columbus Water Treatment Facilities.
Highlights
- Set two temporary 2500KVA transformers and refed the hospital’s existing 1960s double-ended switchgear lineup with 20 sets of 750Al. 10 to each side.
- Demoed out the four old AEP transformers and 4000amp bus duct from the existing underground electrical vault.
- Installed a new (G&W) primary transfer switch that will transfer upon loss of one of the two AEP circuits that feed the hospital.
- Installed a new double-ended substation with 3000KVA transformers.
- Installed six new bus ducts that had to tie into the existing bus ducts that feed the normal power to the hospital.
$2M
contract
Outdated
equipment posed challenges
0
downtime in water flow






