The Ohio State University, Lacrosse Stadium

LocationColumbus, Ohio Contract$2.7 Million RoleElectrical Contractor Construction ManagerRuscilli Construction Completion2023

The new lacrosse-dedicated stadium boasts 360-degree vantage points, and night-time play thanks to the seven 80’ sports lighting structures installed by Claypool Electric. The facility features two electric services and an extensive multi-media infrastructure.

CHALLENGES

Due to supply chain shortfalls, the distribution equipment was scheduled to arrive after the inaugural season was complete. This challenge required Claypool Electric to develop a creative solution.

OUTCOME

Claypool Electric coordinated a plan with the owner, building department and all other stakeholders to use temporary equipment, enabling play for the entire season.

HIGHLIGHTS

The project was completed in time for the opening day.