John and Mary Alford Center for Science and Technology, The Ohio State University
LocationNewark, Ohio Contract$3,808,000 RoleElectrical and Technology Subcontractor Construction ManagerSmoot Construction Completion2021
A new three-story, 61,000-square-foot building on the Newark campus of The Ohio State University, this Science and Technology Lab and Research Building consists of a medical simulation lab, cadaver labs, physics labs, biology labs, chemistry labs, geology lab, spider lab, research labs, and classrooms.
CHALLENGES
Budget constraints and a challenging schedule.
OUTCOME
Despite the pandemic occurring in the midst of the project, and multiple delays to predecessor work, Claypool Electric completed its work on schedule.
HIGHLIGHTS
Sophisticated lighting and controls.